MV/MV Electrical substation 13.8/34.5kV 50MVA

Cayo Cruz (Cuba)

Country

Cuba

Year

2022

Description

Study, design, construction and supply of electrical substation equipment addressed to n. 8 diesel turbines in Cayo Cruz, Cuba.

  • N. 36 MV AIS Metal Clad switchgear cubicles 34.5kV and 13.8kV with Arc-proof system
  • Power transformer 25MVA
  • Low-voltage panels Euro SDS
  • Protection panels Euro P&C
  • SCADA system
  • HVAC system
  • Firefighting plant

Our Engineers have developed the protection and automation SCADA system with a new and more user-friendly Human-Machine Interface, that allows better fruition and control of the energy plant. In order to allow parallel monitoring from different operator control rooms, we installed two servers with primary and secondary SCADA systems.

Related projects to SCADA Solution

Nr 2 E-HOUSE 33kV SWITCHING STATION – BUMPER FOR BESS

We are currently engaged in a new project, involving the construction of two MV Switching stations for an upcoming Battery Energy Storage System (BESS) initiative. These stations will be situated in Severalles Farm, Ilmer, Princess Risborough, UK, supplying 100MWh as storage capacity.

N.7 Photovoltaic Plants for a total Power of 15 MW

Granma, Pinar del Rio, Ciego da Avila, Santiago de Cuba, Guantanamo (Cuba)

The project, which has allowed to produce energy locally, has included n. 7 photovoltaic plants located in 5 different Cuban provinces: Granma, Pinar del Rio, Ciego da Avila, Santiago de Cuba and Guantanamo.