Public lighting 30/200/750 Lux
Havana – Plaza de la Revolución (Cuba)
Country
Year
Location
Solutions
Products
Description
The ambitious project, carried out in just three months and inaugurated on the occasion of the May 1st, 2019 parade, guarantees a high energy-efficient lighting system in the stunning Plaza de la Revolucion.
The plant includes n. 2 low (LV) and medium voltage (MV) compact substations STC-Kiosk and n. 8 light towers (n. 4 of which are 35 meters high and n. 4 are 38 meters high). The lamps can operate at three different lighting levels. Each installation includes:
- 30 lux during the night;
- 250 lux for events;
- 750 lux when concerts or television events take place.
Related projects to SCADA Solution
Nr 2 E-HOUSE 33kV SWITCHING STATION – BUMPER FOR BESS
We are currently engaged in a new project, involving the construction of two MV Switching stations for an upcoming Battery Energy Storage System (BESS) initiative. These stations will be situated in Severalles Farm, Ilmer, Princess Risborough, UK, supplying 100MWh as storage capacity.
MV Substation 34.5kV
Artemisa (Cuba)
The project has been carried out in the famous industrial center in Artemisa. It has included accessories for an electrical substation 34,5kV and the associated substation "Switching Center".