N. 6 Transformation cabins 13.8kV and 34.5kV for electrical grid

Havana (Cuba)

Country

Cuba

Year

2020

Description

The project has involved the engineering, construction and supply of n. 6 STC-Kiosk, which have been integrated into the Cuban public grid. These small size substations have been refined with high-resistant painting, suitable for Caribbean humid and saline environments, and customized with internal equipment.

N.3 ring-configuration transformation centres 13,8kV 630kVA 415-240V 60Hz, and N.3 ring-configuration transformation centres 34,5kV 400kVA 415-240V 60Hz, containing:

  • Medium-voltage (MV) gas-insulated ATR-Ring switchgears 24kV
  • Low-voltage (LV) Euro P&C switchboard 630A 25kA
  • RTU for connection to SCADA system
  • Firefighting system
  • Electric meter
  • Temperature sensors
  • Smoke detectors
  • Alarm system
  • Protection relays

Related projects to Transformation cabin

N. 4 TRANSFORMATION CABINS FOR PHOTOVOLTAIC SYSTEM 3.15MVA

Viterbo (Italy)

Design, manufacturing and supply of nr. 4 modular and plug-in Solar Stations, STC-Kiosk, for the photovoltaic system in Viterbo, Italy.

N. 3 MV Transformation cabins 13.8kV for the new boulevard in Varadero

Varadero (Cuba)

The project consists of three transformation cabins addressed to the new Varadero boulevard, in Cuba. It is located in one of the main arteries of the famous Cuban tourist center, where shops and restaurants will be able to carry out their business also thanks to the electricity grid implemented by the C.R. Technology Systems team.