THE NEW BOULEVARD IN VARADERO

Varadero (Cuba)

Country

Cuba

Year

2020

Description

The project consists of three E-Houses addressed to the new Varadero boulevard, in Cuba. It is located in one of the main arteries of the famous Cuban tourist center, where shops and restaurants will be able to carry out their business also thanks to the electricity grid implemented by the C.R. Technology Systems team.

In detail, the project involves the design, construction and commissioning of three compact and modular electrical substations, STC-Kiosk, with ring configuration 630kVA 13.8kV 230-127V, which house:

  • N. 3 medium voltage (MV) panels insulated in gas (GIS) ATR-Ring 13.8kV 630A 16kA
  • N. 1 transformer 630kVA
  • Euro-PC 220 / 127V 630A 35kA 60Hz low voltage panels
  • RTU panel
  • Protection relay, integrated in the transformer
  • Fire-fighting system
  • Auxiliary electrical equipment

Related projects to STC – Kiosk

N. 4 COMPACT SUBSTATIONS FOR DEVELOPING INDUSTRIAL AREA

Havana (Cuba)

The project was addressed to the developing industrial center of Artemisa and included the engineering study, construction, and commissioning of compact substations for energy distribution and electrical equipment for the substation interconnection.

N. 6 STC-KIOSK FOR SECONDARY ELECTRICAL DISTRIBUTION

Havana (Cuba)

The project has involved the engineering, construction and supply of n. 6 STC-Kiosk, which have been integrated into the Cuban public grid. These small size substations have been refined with high-resistant painting, suitable for Caribbean humid and saline environments, and customized with internal equipment.