N. 4 MV Substations 34.5 and 13.8kV 77.2MVA

Cayo Coco, Cayo Guillermo, Uva Caleta, Flamenco (Cuba)

Description

The ambitious project has seen the creation of four electrical substations addressed to different areas of the Cuban Republic.

Four electrical substations have been designed and put into service:

  • Cayo Coco substation 13,8kV and 34,5kV, which includes Normal Clad electrical switchgears, 2x 16/20MVA power transformers, 13,8kV earthing transformers, Euro-SDS and Euro-P&C low-voltage switchborads, SCADA Pacis data acquisition and control system
  • Cayo Guillermo substation 13,8kV and 34,5kV, which includes Normal Clad electrical switchgears, 2x 10MVA power transformers, 13,8kV earthing transformers, Euro-SDS and Euro-P&C low-voltage electrical switchboards, SCADA Pacis data acquisition and control
  • Flamenco substation 13,8kV and 34,5kV, which includes Normal Clad electrical switchgears. 2x 6,3MVA power transformers, 13,8kV earthing transformers, Euro-SDS and Euro-P&C low-voltage electrical switchboards, SCADA Pacis data acquisition and control system
  • Caleta substation 13,8kV and 34,5kV, which includes metal clad electrical switchgears, 2x 6,3MVA power transformers, 13,8kV landfill transformers, Euro-SDS and Euro-P&C low-voltage switchgears, SCADA Pacis data acquisition and control system
The substations are also equipped with a lighting system, video surveillance and air-conditioning systems, equipment for the interconnection system

Related projects to Electrical substation

MV/MV Substation 34.5/13.8kV 6.3MVA

Pesquero (Cuba)

Design, construction and installation of electrical equipment destined for the revamping and empowerment of an outdoor electrical substation MV/MV 34.5/13.8kV serving a tourist center located in the province of Holguín (Cuba).

HV/MV Substation 110/34.5kV 2x40MVA

Artemisa (Cuba)

The project has included the study, construction, and installation of a hybrid GIS electrical substation, to supply energy to an industrial area in Atemisa.