N. 3 e-Houses for agrivoltaic plants
Naples
Country
Year
Location
Solutions
Products
Description
N. 3 switchrooms for the agrivoltaic park in Giugliano (Naples), with a total nominal power of 86.63 MW and an annual clean energy production of over 130 GWh. This will supply electricity to 48,000 households, avoiding the emission of more than 60,000 tons of CO₂ and improving crop yield and productivity.
The project is part of the ambitious “Terra del Sole” initiative, which aims to mark a new chapter for agriculture and clean energy in Italy. It is the result of a collaboration between entrepreneurs and farmers allied to support the sustainable energy transition, while respecting the land and the hosting community.
The switchrooms are equipped with:
- MV Switchgear ATR 36kV 2500A, 25kA
- LV Switchboards and protection systems
- 100kVA auxiliary transformer
- UPS and batteries for operational continuity
- HVAC system for thermal management
The park covers an area of 130 hectares and is divided into North Field and South Field, connected by an underground medium-voltage duct bank. Over 70% of the area is dedicated to crops, while about 30% hosts photovoltaic structures with elevated panels positioned above the cultivated fields and widely spaced between rows. This configuration allows renewable energy generation without sacrificing agricultural land, while creating shading that enhances agricultural performance in hotter regions. This protection reduces thermal and water stress, improving plant health and resulting directly in higher-quality fruits and vegetables.
Additionally, a large perimeter belt of trees and shrubs will be created to preserve the landscape.
Related projects to eHouse
eHouse for Continosa PV and wind plant 90MVA
Macchiareddu (Italy)
Design, manufacture, and supply of our eHouse, the Switching Station STC-Box for the in the Continosa photovoltaic (PV) and wind park 90MVA, within the industrial area of Macchiareddu (Sardinia).
HV/MV Mobile Substation 110/20kV 40MVA
Fushë-Krujë (Albania)
Development and supply of a mobile substation 110/20kV for transformation and primary distribution 40MVA, carried out in the geographical area of Fushë-Krujës. It involves the supply of electricity for the benefit of a population of over 40,000 inhabitants.