Supply of Electrical Materials for a Photovoltaic Plant
Areza (Eritrea)
Country
Year
Description
The project has been implemented in Areza, a rural area in the south of Eritrea, aimed to supply electrical material for a photovoltaic plant.
It has been installed:
- 13 voltage transformers 200kVA 15000/400/240V;
- 21 voltage transformers 100kVA 15000/415/240V;
- 26 voltage transformers 50kVA 15000/415/240V;
- 30 voltage transformers 25kVA 15000/415/240V.
Related projects
HV/MV Substation 115/6.3kV 4.7MVA
Shpellë (Albania)
Construction of the electrical system of a hydroelectric plant in Shpellë. Hydroelectric energy is based on the conversion of natural water flow into electricity and is classified as renewable energy because it is generated by exploiting the kinetic force given by the natural water cycle.
Normal Clad switchgears 24kV IP65 for Mine
Yauyos (Perù)
The project has the aim to increase the electrical grid of a mine located in the province of Yauyos (Peru) and it has involved the design, construction and supply of n. 7 medium-voltage (MV) Normal Clad switchgear cubicles 24kV 630A 31.5kA and 17.5kV 1250A 31.5kA, with IP65 protection degree, an auxiliary transformer 12600/230V 10kA, materials and accessories necessary for the start-up of the plant.