MV E-House 20kV for Tesla Battery Energy Storage System

West Sussex (United Kingdom)

Country

United Kingdom

Year

2021

Description

Engineering study, design, construction, and supply of n. 1 compact substation STC-Box for a Tesla project in West Sussex (UK).

The big E-House has a length of 11 meters and is equipped with n. 7 medium-voltage (MV) air-insulated ATR cubicles 36kV 800A 17.5kA (1s), low-voltage (LV) switchboard Euro-SDS, interconnection cable, RTU panel, power and auxiliary transformer 50kVA, metering system, HVAC system. ATR switchgear got the IAC 20kA (1s) certification, moreover, it includes internal arc protection sensors, in order to ensure a rapid extinguishing in the event of an arc.

Related projects to eHouse

Nr 2 E-HOUSE 33kV SWITCHING STATION – BUMPER FOR BESS

We are currently engaged in a new project, involving the construction of two MV Switching stations for an upcoming Battery Energy Storage System (BESS) initiative. These stations will be situated in Severalles Farm, Ilmer, Princess Risborough, UK, supplying 100MWh as storage capacity.

MV E-House 35/20/10kV for industrial district

Peshkopi (Dibër) - Albania

Design, construction and supply of a medium-voltage (MV) compact substation in Peshkopi, industrial area of the Albanian city Dibër.