N.2 MV E-House 33kV 50MVA for Tesla Battery Energy Storage System

Yorkshire (United Kingdom)

Country

United Kingdom

Year

2022

Description

Design, construction and supply of n. 2 switching stations equipped with power transformers, MV air-insulated ATR switchgear 36kV 1250A 20kA (1s), LV switchboards, and a SCADA system for the remote control, destined to Tesla BESS (Battery Energy Storage System).

The Pillswood e plant in Yorkshire has a total power of 98 MW.
Our switching stations connect the Tesla Megapack to the electrical grid.

Related projects to eHouse

N. 3 e-Houses for agrivoltaic plants

Naples (Italy)

N. 3 switchrooms for the agrivoltaic park in Giugliano (Naples), with a total nominal power of 86.63 MW and an annual clean energy production of over 130 GWh. This will supply electricity to 48,000 households, avoiding the emission of more than 60,000 tons of CO₂ and improving crop yield and productivity.

MV E-House 35/20/10kV for industrial district

Peshkopi (Dibër) - Albania

Design, construction and supply of a medium-voltage (MV) compact substation in Peshkopi, industrial area of the Albanian city Dibër.