Medium-Voltage (MV) Normal Clad Switchgears 7,2kV 630A 20kA (3s)

Donetsk (Ukraine)

Country

Ukraine

Year

2012

Description

The project has involved the implementation of Normal Clad switchgears, addressed to an important industrial, steel and chemical hub in the city of Donetsk.

It has included the study, construction and implementation of n. 16 air-insulated (AIS) medium-voltage Normal Clad switchgears 7,2kV 630A 20kA (3s).

Related projects

N. 7 MV E-Houses 24kV for generator plants

Guacara e Tucacos (Venezuela)

The project was carried out in Guacara and Tucacas, tourist cities located in Venezuela. It has seen the implementation of several compact substations, destined to Hyundai generator plants.

N. 2 MV E-House 24kV and 36kV for photovoltaic plant

Assemini, Loc. Macchiareddu (Italy)

The project was carried out in an electrical substation for the delivery of high voltage (HV) power, situated inside a photovoltaic plant, in one of the most important industrial centres of the southern Sardinia.