Electrical installation works for industrial plant

Pieve Vergonte (Italy)

Country

Italy

Year

2020

Description

The project has included the works to expand the high-voltage (HV) electrical substation serving the Hydrochem Srl plant in Pieve Vergonte (Piedmont).

C.R. Technology Systems has supervised and coordinated the team and the activities on site, carried out in record times.
In detail, HV electrical equipment was installed and put into service through a process of energizing the substation in two phases, and it included:

  • Transformers
  • Disconnectors
  • Circuit-breakers
  • Line insulators
  • Surge arresters
  • Portal 2 intermediate
  • Portal 2 Side stalls A and B

Related projects to Electrical substation

MV Substation 24kV

Vedado (Cuba)

Design, construction and supply of electrical equipment destined for the new 5-star hotel "Torre K" in Vedado, in Havana.

N.2 HV/MV Substations 110/7.3kV 8MVA

Çemericë, Korçë (Albania)

The project has seen the implementation of 2 high-voltage to medium-voltage electrical substations in Çemericë and Korçë.