Electrical installation works for industrial plant

Pieve Vergonte (Italy)

Country

Italy

Year

2020

Description

The project has included the works to expand the high-voltage (HV) electrical substation serving the Hydrochem Srl plant in Pieve Vergonte (Piedmont).

C.R. Technology Systems has supervised and coordinated the team and the activities on site, carried out in record times.
In detail, HV electrical equipment was installed and put into service through a process of energizing the substation in two phases, and it included:

  • Transformers
  • Disconnectors
  • Circuit-breakers
  • Line insulators
  • Surge arresters
  • Portal 2 intermediate
  • Portal 2 Side stalls A and B

Related projects to Electrical substation

HV Substation 132kV

Adria, Loc. Smergoncino (Italy)

The project, result of an important partnership, is addressed to a historical industrial company located in Smergoncino, in Rovigo area. The long-lasting know-how gained in the high-voltage field has made it possible to increase the plant power supply.

HV Substation 35/110kV 15MVA

Tirana (Albania)

The project has included the construction of an electrical substation in Albania.