MV/LV Cement transformation cabin 15/0.8kV for photovoltaic system

Cuneo (Italy)

Country

Italy

Year

2022

Description

We have carried out an STC-Kiosk transformation cabin, destined for a photovoltaic system in the province of Cuneo, in Piedmont.

Our Engineering Hub has designed, constructed and installed an MV/LV 15/0.8kV 1MVA cement transformation cabin, equipped with an air-insulated (AIS) medium-voltage (MV) electrical switchgear ATR 24kV 630A 16kA, low-voltage (LV) Euro-SDS panels, LV disconnector with fuses 800V AC, dry-type elevator transformer, interconnecting cables and auxiliary equipment. This tailor-made project was completed in a few weeks, thanks to the know-how and flexibility of our engineers. To speed up work, we made the roof removable, in order to install the transformer in a second phase.

Related projects to Photovoltaics

STC-Skid transformation cabins 4,8MVA

Padua (Italy)

Design, manufacturing and commissioning of plug-in Skid transformation cabins destined for a photovoltaic plant in the beautiful location of Monselice (Padua).

N. 6 Photovoltaic Plants for a total power of 10MW

Latin America

It is the first major project concerning 6 photovoltaic plants distributed in five different provinces, which has the function of reducing CO2 emissions and safeguarding the surrounding environment, threatened by the increasing rate of tourism.