The project has been implemented in Areza, a rural area in the south of Eritrea, aimed to supply electrical material for a photovoltaic plant.
It has been installed:
- 13 voltage transformers 200kVA 15000/400/240V;
- 21 voltage transformers 100kVA 15000/415/240V;
- 26 voltage transformers 50kVA 15000/415/240V;
- 30 voltage transformers 25kVA 15000/415/240V.
Related projects
Photovoltaic plant 25MWp and GIS substation 60kV
Caraculo (Angola)
Design, construction, supply of the electrical equipment for a photovoltaic plant 25MWp and 60kV GIS substation in Angola.
N. 2 MV E-Houses 33KV 25MVA and 50MVA for BESS
Hawkers Hill, Skelmersdale (United Kingdom)