Supply of Electrical Materials for a Photovoltaic Plant

Areza (Eritrea)

Country

Eritrea

Year

2018

Location
Products
Description

The project has been implemented in Areza, a rural area in the south of Eritrea, aimed to supply electrical material for a photovoltaic plant.

It has been installed:

  • 13 voltage transformers 200kVA 15000/400/240V;
  • 21 voltage transformers 100kVA 15000/415/240V;
  • 26 voltage transformers 50kVA 15000/415/240V;
  • 30 voltage transformers 25kVA 15000/415/240V.
In addition, the project has included over n. 6000 circuit breakers, n. 170 disconnectors and various types of cables and connectors. The n. 2 viallges in Aresa and Maidma have been interconnected to n. 2 photovoltaic plants of total power 2.7MWp.

Related projects

Skid transformation cabin 36kV 4.4MVA

Trino Vercellese (Italy)

We have designed, manufactured and carried out the commissioning of STC-Skid transformer substations destined for the Trino Vercellese photovoltaic plant.

N. 4 MV E-Houses 23kV for electrification of rural areas

Gonaives e Cabo Haitiano (Haiti)

The project has included n. 4 compact substations, with the aim to supply the electricity in the rural areas of Gonaives and Cabo Haitiano.