Supply of Electrical Materials for a Photovoltaic Plant

Areza (Eritrea)

Country

Eritrea

Year

2018

Location
Products
Description

The project has been implemented in Areza, a rural area in the south of Eritrea, aimed to supply electrical material for a photovoltaic plant.

It has been installed:

  • 13 voltage transformers 200kVA 15000/400/240V;
  • 21 voltage transformers 100kVA 15000/415/240V;
  • 26 voltage transformers 50kVA 15000/415/240V;
  • 30 voltage transformers 25kVA 15000/415/240V.
In addition, the project has included over n. 6000 circuit breakers, n. 170 disconnectors and various types of cables and connectors. The n. 2 viallges in Aresa and Maidma have been interconnected to n. 2 photovoltaic plants of total power 2.7MWp.

Related projects

Retrofit of Medium-Voltage (MV) Circuit Breakers

Dalmine, BG (Italy)

Design and implementation of medium-voltage circuit-breakers, HD4-RG and HD4-MG models for the retrofit of the medium-voltage switchgears.

EHOUSE FOR WATER TREATMENT PLANT

Arezzo (Italy)

We have designed and manufactured a 1600kVA STC-Kiosk transformer cabin