Supply of Electrical Materials for a Photovoltaic Plant
Areza (Eritrea)
Country
Year
Description
The project has been implemented in Areza, a rural area in the south of Eritrea, aimed to supply electrical material for a photovoltaic plant.
It has been installed:
- 13 voltage transformers 200kVA 15000/400/240V;
- 21 voltage transformers 100kVA 15000/415/240V;
- 26 voltage transformers 50kVA 15000/415/240V;
- 30 voltage transformers 25kVA 15000/415/240V.
Related projects
Skid transformation cabin 36kV 4.4MVA
Trino Vercellese (Italy)
We have designed, manufactured and carried out the commissioning of STC-Skid transformer substations destined for the Trino Vercellese photovoltaic plant.
N. 4 MV E-Houses 23kV for electrification of rural areas
Gonaives e Cabo Haitiano (Haiti)