N. 7 MV E-Houses 24kV for generator plants

Guacara e Tucacos (Venezuela)

Country

Venezuela

Year

2010

Location
Solutions
Products
Description

The project was carried out in Guacara and Tucacas, tourist cities located in Venezuela. It has seen the implementation of several compact substations, destined to Hyundai generator plants.

The project has included the design, implementation, and supply of electrical equipment, addressed to two different areas:

  • In Guacara were supplied n. 4 STC-Box shelters, with Normal Clad cubicles 13.8kV 2000A 31.5kA, with a frequency of 60Hz for the diesel power station consisting of n. 56 units 1700kW each.
  • In the city of Tucacas, were supplied n. 3 STC-Box shelters, with Normal Clad cubicles 13.8kV 2000A 31.5kA, with a frequency of 60Hz for the diesel power station consisting of n. 48 units 1700kW each.

Related projects to eHouse

N. 3 e-Houses for Gallitello substation 30/220kV

Gibellina (Italy)

Design, manufacturing and supply of n. 3 switchrooms for Gallitello connection substation 30/220kV in Gibellina area. It is an essential element for strengthening the region’s energy resilience and integrating renewable energy sources into the Sicilian national transmission grid.

EHouse and n. 4 transformation cabins for Photovoltaic plant

Macchiareddu (Italy)

Project realised in Macchiareddu, within a photovoltaic park in Sardinia in one of the most important industrial hubs. This is an area of development increasingly powered by alternative energy, where CR Technology Systems has already been present for some years in the realisation of green projects in the area.