Powering the king: eHouses for project Mufasa
Vlissingen
Country
Year
Description
We have designed, manufactured and supplied n. 5 eHouses for the Battery Energy Storage System (BESS) in Vlissingen, a key hub for renewable energy in the Netherlands.
The great project, called Mufasa, is one of the BESS plant largest ever built in Europe and will replace a former coal-fired power plant connection to the high-voltage grid.
Technical features:
- N. 4 Switchrooms equipped with ATR MV switchgear 36kV, LV panels with Swicom technology, HVAC system, fire detection system, UPS and rectifiers, roxtech, patch panels, HV protection panels.
- N. 1 Control room equipped with HVAC system, fire detection system, UPS and rectifiers, roxtech, patch panels, HV transformer protection panels.
Related projects to eHouse
eHouse for 35MW/70MWh Skeeby BESS
North Yorkshire
Design, manufacturing and supply of a switchroom for the 35MW/70MWh Skeeby Battery Energy Storage System (BESS), located just outside Richmond in North Yorkshire.
N. 7 MV E-Houses 24kV for generator plants
Guacara e Tucacos (Venezuela)
The project was carried out in Guacara and Tucacas, tourist cities located in Venezuela. It has seen the implementation of several compact substations, destined to Hyundai generator plants.