Description

The projectincludes the supply of two mobile substations in the south of Albania, Fushë Krujë and Fier, where the Government has invested a huge amount of money in order to increase the supply of electrical grid.

The project, commissioned by the Albanian electricity authority, consists of two mobile substations medium-to-medium-voltage (MV/MV) 7,5MVA 35/10,5/6,3kV and medium-to-low-voltage (MV/LV) 630kVA 20/10/0,4kV. The supply has included generators 125kVA, transformers up to 7,5MVA, medium-voltage metal-enclosed ATR switchgears, low-voltage Euro PC and Euro SDS switchgears.

Related projects to Mobile Substation

N. 2 Mobile Substations 132kV

Bassora (Iraq)

These are the first mobile substations projected and realized by C.R. Technology Systems S.p.A. and are used to provide electricity to remote areas.

Mobile Substation 115/37,5/10,5kV 10MVA and Transformer 123kV

Udënisht, Korçë (Albania)

The project has seen the installation of a mobile substation in Udënisht, a well-known touristic area, in Korçë, the sixth most important town in Albania.