eHouses for thermoelectric power plant

Chieti (Italy)

Country

Italy

Year

2024

Description

Design, construction and supply of n. 2 plug-in cabins for the Thermoelectric Power Plant in Chieti, Italy.

  • N. 1 e-House equipped with MV electrical switchgear 7.2kV 1250A 40kA(1s), n. 2 power transformers 350kVA, LV connection cables, air conditioning system, auxiliary equipment.
  • N. 1 e-House equipped with LV Power center panel, UPS, certified fiscal meters with GSM communication, air conditioning system, auxiliary equipment and provision for control station.
The project is destined to Gissi Thermoelectric Power Center, in Chieti. This plant works with a combined cycle to produce electricity, using only natural gas, with a power of approximately 840MW.
The system allows to optimize the use of fuel and to minimize the environmental impact, recovering the residual heat of the exhaust gases to produce additional energy.

Related projects to Power station

eHOUSE FOR SCOTTISH BESS SYSTEM

Rothienorman (Scotland)

We have designed, manufactured and supplied an eHouse 33kV and control room destined to a Battery Energy Storage System (BESS) in Rothienorman, Scotland.

eHOUSE: the smart solution for energy distribution

Latin America

We have designed and manufactured n. 5 compact plug-in substations for MV and LV electricity distribution at a territorial level, primarily designed for hotel facilities. The cabins are part of a unified MV distribution system with a double-ring configuration.