N. 2 Transformation cabins for industrial areas

Artemisa (Cuba)

Description

Design, construction, installation of n. 2 STC-Kiosk transformation centers with ring configuration addressed to industrial areas in Cuba.

Technical features:

  • STC-Kiosk MV/LV 1600kVA 34,5kV/415-240V for detergent factory
  • STC-Kiosk 200kVA 34,5/0,220/0,127kV
  • Equipped with medium voltage gas-insulated switchgears ATR-Ring 36kV 630A 16kA, transformer, LV panels Euro SDS, auxiliary equipment.
  • Surge arrester directly on the bushing
The STC-Kiosk is a plug-in compact substation that optimizes spaces and can be remotely controlled.

Related projects to Transformation cabin

Electrical equipment for rooftop photovoltaic system 1.8MWP

Artemisa (Cuba)

Our engineers and technicians have studied, designed and assembled electrical equipment addressed to a rooftop photovoltaic system 1.8MWP in an industrial area in Artemisa (Cuba).

Photovoltaic Plants 10MWp

Venegas, Matanzas, Camagüey, Mayajigua (Cuba)

The project includes n. 4 photovoltaic plants, with a total of 10MWp, located in 4 sites, situated in 3 different provinces of the Cuban Republic. It is part of the implementation plan of the Cuban economic development program, with the aim to reach a total of 700MW photovoltaic power supply by 2030.